Roadway and Drainage Improvements to Bellaire Boulevard and Westmoor Drive
Bellaire Boulevard and Westmoor Drive were designated for roadway and drainage improvements as part of the Fort Bend County 2017 Mobility Program. The project scope includes a two-lane concrete boulevard with curb and gutter to complete the second half of a four-lane concrete boulevard for both roadways. Drainage will include additional curb inlets and manholes to tie into the existing trunk line. A portion of the trunk line will be constructed along Westmoor Drive to tie into the existing storm sewer. The total length of the project is 5,100 linear feet with the following project limits:
- Bellaire Boulevard – 500’ west of FM 1464 to Westmoor Drive
- Westmoor Drive – Bellaire to FM 1093
Additionally, sidewalk will be placed along the east side of Westmoor Drive between Bellaire Boulevard and Scrub Oak Drive. The estimated construction duration is 6 months.